PORTLAND, Oregon — November 24, 2026. A Portland land-use hearings officer granted conditional approval for Portland General Electric's (PGE) transmission-line upgrades near Forest Park and the Harborton Substation. The city published the decision on November 20. The appeal deadline is 4:30 p.m. December 4.

What the project would do

According to the city's decision materials, the work would affect approximately 4.7 acres of natural resources, remove 375 living and 18 dead trees, relocate an existing power pole, install two new poles and create a roughly 1,400-foot section of 230-kilovolt transmission lines. The proposal also affects wetlands and streams.

Why the sides disagree

PGE says the upgrades are necessary to maintain reliability, with transmission-system constraints expected from 2028. Portland Business Journal reports that PGE agreed to provide $5.5 million for environmental mitigation under a settlement with the city.

Environmental and neighborhood advocates argue that the project would cause unacceptable ecological harm. Forest Park Neighborhood Association has said it plans to appeal. A plan to appeal is not confirmation that an appeal has already been filed or upheld.

Next steps

The deadline for appeals is December 4. Any further administrative or legal decisions could affect the project's timeline.

Sources: Portland land-use notice, November 20; official decision document; Portland Business Journal, November 23.